Skip to main content
561-517-0959
Custom Home Building
Ground-up luxury homes across South Florida
Home Additions
Guest suites, second stories, expansions
Interior Renovations
Kitchens, bathrooms, whole-home transforms
Design-Build
One team from design through construction
Site Due Diligence
Zoning, feasibility, and preconstruction analysis
Project Gallery
Browse all completed homes
Project Map
Explore our work on an interactive map
View All Areas →
AboutBlogContact
Contact Us
Process

What Happens in Pre Construction: The Months Before Ground Breaks

Chase Lamson, President of SouthShore Builders
Chase Lamson··8 min read
Pre-construction planning for a custom home in Palm Beach County

People picture a custom home starting with a bulldozer. It does not. By the time equipment shows up, the budget, the schedule, and most of the quality outcome are already set.

Pre construction is the part nobody photographs and the part that decides everything. Here is what actually happens.

The Short Answer

Pre construction is everything between the decision to build and the first day on site: feasibility and lot due diligence, schematic design, budget development, engineering, selections, and permitting. On a Palm Beach County custom home it typically runs six to twelve months, and it is where the budget and schedule are actually determined.

6 to 12 monthsTypical pre construction duration on a Palm Beach County custom home, from first feasibility work to an issued building permit.

Phase 1: Feasibility and due diligence

Before design, the lot has to be understood. Zoning district, setbacks, lot coverage, height limits, flood zone and required finished floor elevation, survey, soil borings, tree survey, utility availability, and any HOA or design review requirements.

This phase answers one question: what can be built here, and roughly what does it cost. It is inexpensive relative to everything that follows, and it prevents the worst outcome in custom building, which is designing a house that does not fit the site or the budget. Our site due diligence service exists for this stage.

Phase 2: Schematic design

The architect develops the concept. Massing, floor plan, room relationships, how the house sits on the lot, how it addresses the water or the street.

The critical discipline here is that the builder prices as the design develops. Not once at the end. A schematic level budget catches the ten thousand square foot idea on a budget for six thousand while it is still a drawing.

Phase 3: Budget development

This is where the itemized budget gets built. Every division, every allowance, every exclusion, written down.

A real budget at this stage shows you the tile allowance per square foot, the window package, the site work, the mechanical scope, and the contingency. A single number does not. This is the document you should be comparing between builders, and it is the document that keeps the project honest for the next two years.

Carry a contingency of ten to fifteen percent. Not because the builder expects to be wrong, but because custom homes uncover things.

Phase 4: Design development and engineering

The design gets resolved into a buildable set. Structural engineering for wind and, on coastal sites, flood and elevation requirements. Mechanical, electrical, and plumbing coordination. Energy calculations. Product approvals for impact rated openings and roofing assemblies.

This is also where value engineering happens if the budget needs adjusting. It is far cheaper to change a roof geometry on paper than after the trusses are ordered.

Phase 5: Selections

Selections start earlier than most owners expect. Structural and long lead items first: windows and doors, roofing, exterior finish, appliances that affect cabinetry and mechanical, plumbing fixtures that affect rough in.

Then finishes. Tile, stone, cabinetry, hardware, lighting, paint.

The reason to front load this is simple. Every selection made after the related work has started becomes a change order, and change orders are how schedules and budgets slip. Deciding early is uncomfortable. Deciding late is expensive.

Phase 6: Permitting

The completed set goes in for review. In Palm Beach County that means the building department, and depending on the location, historic review, coastal review, HOA architectural review, or a town design board.

Plan on roughly two to five months for a new custom home, driven by drawing completeness and the number of review cycles. Complete, coordinated drawings on the first submittal is the single biggest lever on this timeline.

Phase 7: Pre construction planning

Before mobilization: the construction schedule with real durations and dependencies, subcontractor buyout, long lead material orders placed, site logistics planned, builder's risk insurance bound, and the communication cadence set.

Then the equipment arrives, and everything that was decided on paper starts to become a house.

Why this phase deserves your patience

Early in the process?

The sooner a builder is in the room, the better your budget holds. Start with a conversation about your lot and your plan.

Start With a Conversation

Owners are usually eager to see something happen. Understandable. But the projects that run smoothly are almost always the ones where pre construction was not rushed.

Time spent here is cheap. Time spent fixing decisions during construction is not. For the construction side of the timeline, see our guide to how long it takes to build a custom home in Palm Beach County.

If you are at the beginning of this, start a conversation. The earlier a builder is in the room, the better your budget holds.

Frequently Asked Questions

How long does pre construction take on a custom home?

Typically six to twelve months in Palm Beach County, covering feasibility, design, engineering, budgeting, selections, and permitting. Complex coastal sites and projects that require design review board approval sit at the longer end.

When should the builder get involved?

During design, not after. A builder pricing the design as it develops keeps the drawings and the budget aligned. Bringing a builder in only after a full set of drawings is complete is the most common way projects end up 30 to 40 percent over budget.

Do I pay for pre construction services?

Often yes. Feasibility work, preliminary budgeting, and value engineering during design take real time. Many builders charge a pre construction fee, and some credit it toward the construction contract. Ask how it is handled before you start.

How many selections do I have to make before construction starts?

More than most people expect. Structural and long lead items must be locked before the permit set is finalized, and finish selections should be substantially complete before framing. Late selections are the leading cause of schedule slip.

Can I start site work before the full permit is issued?

Some jurisdictions allow early permits for demolition, tree work, or site preparation ahead of the main building permit. Whether that helps depends on the schedule. Never start permitted work without the permit in hand.

Planning a project in South Florida?

SouthShore Builders is based in Delray Beach and builds across Palm Beach County and Broward County.

Schedule a Consultation →|Call 561-517-0959
Chase Lamson
Chase Lamson

President, SouthShore Builders

Chase Lamson leads SouthShore Builders with decades of South Florida custom home experience. SouthShore is a licensed general contractor serving Palm Beach County and Broward County.

Keep Reading

Related Posts

Ready to Start Your Project?

SouthShore Builders is licensed, local, and ready to discuss your custom home or renovation.

Call 561-517-0959Send a Message