If you are building in Palm Beach County, your project will spend part of its life in hurricane season. A twelve to twenty month schedule crosses at least one, usually two.
This is normal, and it is manageable. What it requires is a builder with a plan written before the season rather than assembled the day a storm is named.
The Short Answer
During hurricane season a builder should have a written storm plan covering site securing, material and equipment tie down, debris removal, temporary structure bracing, and communication with the owner. Coverage comes from a builder's risk policy carried during construction, which is separate from your homeowners policy. Confirm who carries it, what the wind and named storm deductibles are, and what the plan is before a storm is named.
What a real storm plan covers
Before the season starts:
- The site is organized so it can be secured quickly
- Material deliveries are scheduled with storm risk in mind
- Temporary structures, scaffolding, and fencing are installed so they can be taken down or braced
- Trades are briefed on the sequence and the trigger points
- Contact list and communication plan are set with the owner
When a storm enters the forecast cone:
- Loose material is removed from site or secured
- Dumpsters are emptied or hauled
- Scaffolding and temporary structures come down or get braced
- Openings on a dried in structure are protected
- Excavations and trenches are addressed for water and collapse
- Equipment is moved off site or tied down
- Photos are taken to document site condition before the event
- The owner is told what was done and when
After the storm:
- Site inspected before anyone works
- Damage documented and reported
- Water removed, debris cleared
- Structure and shoring inspected before work resumes
- Schedule impact assessed and communicated honestly
Builder's risk insurance
The single most important thing to confirm before construction starts is who carries the builder's risk policy and what it covers.
This policy covers the structure and materials during construction. It is not your homeowners policy, which typically starts at completion. Ask for:
- Who is the named insured and who is the additional insured
- The policy limit relative to the full construction value
- The wind and named storm deductible, which in Florida is often a percentage rather than a flat amount
- Whether materials stored off site and in transit are covered
- What happens if the project runs past the policy term, which is common
A percentage based named storm deductible on a multimillion dollar project is a real number. You want to know it in advance, not after.
Stage matters
Not every point in a build carries the same risk.
A slab and foundation are resilient. A framed but open structure is the most exposed condition, particularly with trusses set and no sheathing or roofing. A dried in structure with a completed roof and protected openings is in a much better position.
Where a South Florida builder earns their fee is in sequencing. Getting a project dried in ahead of peak season, when the schedule allows it, is worth real effort. That is a conversation to have during scheduling, not in August.
Schedule expectations
Build weather contingency into the schedule from the start. A named storm that passes nearby typically costs several days between preparation, the event, and site recovery. A direct impact costs more, and regional effects on labor and material supply can extend beyond your site.
A schedule with zero weather allowance in South Florida is not a schedule. It is a wish.
Our guide to how long a custom home takes in Palm Beach County covers the full timeline picture.
What to ask your builder before June
Planning a build that starts this year?
Ask us the six questions in this article. We will answer all of them in writing, including our storm plan and builder's risk certificate.
Ask About Our Storm Plan- What is your written storm plan for my site?
- At what point in the forecast do you trigger it?
- Who carries builder's risk, and can I see the certificate?
- What is the named storm deductible?
- How will you communicate with me before and after an event?
- Where will my project be in the sequence by peak season?
A builder who answers those six clearly has done this before. A builder who has to go find out has not.
If you are planning a build that starts this year or next, let us walk you through how we handle it.
Frequently Asked Questions
Who insures a house while it is under construction?
A builder's risk policy covers the structure and materials during construction. It is separate from a homeowners policy, which typically begins at completion. Confirm in writing who carries the builder's risk policy, what the limits are, and what the wind and named storm deductibles are before construction starts.
Does construction stop during hurricane season?
No. Work continues throughout the season. Activity pauses only when a specific storm threatens, at which point the site is secured, and it resumes once conditions allow and the site has been inspected.
How much schedule should I allow for storms?
Build weather contingency into the schedule rather than treating every event as a surprise. A named storm typically costs several days between preparation, the event itself, and getting the site back in working order. A major impact costs longer, particularly if regional supply and labor are disrupted.
What happens to materials on site when a storm is coming?
Loose material is removed or secured, dumpsters are emptied or removed, temporary structures and scaffolding are taken down or braced, openings are protected, trenches and excavations are addressed, and equipment is moved or tied down. This work should be planned before the season, not improvised.
Is a house safer at some stages than others?
Yes. A structure that is dried in with a completed roof and protected openings is in a much better position than a framed structure that is open, and a slab is more resilient than either. Sequencing that gets a project dried in ahead of peak season is a real scheduling consideration in South Florida.
Planning a project in South Florida?
SouthShore Builders is based in Delray Beach and builds across Palm Beach County and Broward County.